Project Time Management – Part 2 Activity Sequencing
|
February 26, 2017
|
Project Management
In the previous post on Project Time Management, I talked about the first process, activity definition. Activity definition identifies the deliverables at the lowest level in the work breakdown structure. After you have this list, what do you do with it? You put them in order. Activity sequencing involves identifying and documenting the logical relationships among scheduled activities (PMBOK 130). The deliverables are put in a logical order of precedence. The outputs of the activity definition provide the inputs for the activity sequence process.
- Project Scope Statement
- Activity list
- Activity attributes
- Milestone list
- Approved change request
- Finish to start – the activity can not begin until the previous activity is complete.
- Finish to finish – the activity can not finish until the previous activity is finished.
- Start to start – the activity can not start until the previous activity has started.
- Start to finish – the activity can not finish until the previous activity has started.