• Recent Posts

  • Categories




  • Paper-like Screen The Kindle
    Utilizing a new high-resolution display technology called electronic paper, Kindle provides a crisp black-and-white screen that resembles the appearance and readability of printed paper. The screen works using ink, just like books and newspapers, but displays the ink particles electronically. It reflects light like ordinary paper and uses no backlighting, eliminating the glare associated with other electronic displays. As a result, Kindle can be read as easily in bright sunlight as in your living room.The screen never gets hot so you can comfortably read as long as you like.
  •  

    December 2007
    M T W T F S S
    « Nov   Jan »
     12
    3456789
    10111213141516
    17181920212223
    24252627282930
    31  
  • Inventory program test site

    If you want to try the inventory program you can go here. Inventory Program
  • RSS Word of the Day

  • World Market Quotes


    Forex Rates


    (?)

    « Manage Integrated Change Control | Home | I passed the PMP certification test »

    Performance Measurement Analysis

    By Raymond Keckler | December 2, 2007

    Earned value technique

    This compares what you will produce to what you have already done. You use the earned value technique to continuously monitor the planned value, earned value and the actual costs spent. These can give you variances that will help keep the project on target for the cost and schedule. Knowing the variances will allow the project manager to make corrective actions. The three values must be known to calculate variances

    Planned value (PV) is the cost of work that has been budgeted for a schedule activity or a WBS component. PV is also called budgeted cost of work scheduled (BCWS). Notice that PV is based on the schedule.

    Actual cost (AC) is the cost of completing the work in a given time period. Actual cost could include direct and indirect costs. Only use costs that have been budgeted for the scheduled activity.

    Earned value (EV) is the value of the work completed to date as it compares to the budgeted amount assigned to the work component. EV is also called budgeted cost of work performed (BWCP).

    All values computed will be based on cost so the graph will be a S curve.

    Cost variance (CV) tells you whether you costs are higher or lower than the budgeted amount.

    Schedule Variance (SV) tells you whether you are ahead or behind schedule.

    SV and CV are efficiency indicators.

    Cost and schedule performance indexes are used to calculate the performance efficiencies. They can be used to predict future performance.

    Cost performance index (CPI)

    CPI = EV / AC

    Schedule performance index (SPI)

    SPI = EV / PV

    Results greater than 1 shows good performance.

    Results lower than 1 shows poor performance.

    Results equal to 1 in expect performance.

    Forecasting uses the information gathered to date to estimate the future performance of the project. The two techniques in forecasting is estimate to complete (ETC) and estimate at completion (EAC). They each have three variation and use the budgeted at completion (BAC) cost. BAC is the amount budgeted for the project.

    Estimate to complete (ETC) forecasts how much it will cost to complete the work remaining. We can get the first variance just by adding up the cost of the remaining work that needs to be done. The other two calculations use the earned value data.

    If future costs variances will be similar to the types of variances you seen to date:

    ETC = (BAC -EV) / CPI

    If future costs variances will not be to the types of variances you seen to date:

    ETC = (BAC - EV)

    Estimate at completion (EAC) forecasts the expected total cost of the project.

    If the original assumptions used when estimating were flawed or changes have occurred that changed the original estimates:

    EAC = AC + ETC

    Use this formula when variances are typical:

    EAC = AC + ((BAC - EV) / CPI

    Use this formula when the variances are atypical:

    EAC = AC + BAC - EV

    Finally variance at completion calculates the difference between the budget at completion and the estimate at completion:

    VAC = BAC - EAC

    Raymond Keckler

    Other Articles

    Topics: Project Management |

    Comments